Giving Bookstore About Us Publications Contact Us ABPS
Volunteer Ministries Home Opportunities List Group Projects Current Needs White Cross Contact Volunteer Ministries Volunteer Stories NM Home
  
Volunteers in Mission

Photos from the 2008 Blitz Build for Gulf Coast Hurricane Victims with Habitat for Humanity

Click on the images to see a larger view.
Before the Build
As of February 2008, street signs are in place.   Sewer and electric are ready to go   Next to come are foundations and of course more than 200 American Baptist volunteers  

As of February 2008, street signs are in place. 

 

Sewer and electric are ready to go. 

 

Next to come are foundations and of course more than 200 American Baptist volunteers.

 
Sunday, April 27, 2008

The foundations are poured and marked, wall sections and roof trusses delivered.  The first five sites are ready to go

 

The foundations are poured and marked, wall sections and roof trusses delivered.  The first five sites are ready to go

  The foundations are poured and marked, wall sections and roof trusses delivered.  The first five sites are ready to go  

The foundations are poured and marked, wall sections and roof trusses delivered.  The first five sites are ready to go.

Monday, April 28, 2008
blessing of the walls and washing of hands   Homeowner Carlas nails her first nail   Homeowner Shemico nails her first nail  

The day began with the blessing of the walls. The House and Crew leaders washed their hands as the homeowners watched.

  Homeowner Carlas nails her first nail.  

Homeowner Shemico nails her first nail as volunteers cheer her on.

 
Homeowner Bridget and Crew Leader Bob   Homeowner Madeline nails her first nail   Lots of Lifting  

Homeowner Bridget and Crew Leader Bob take a break as they get to know each other.

 

Homeowner Madeline nails her first nail.

  There was lots of lifting and holding of the walls.  
holding walls in place   there was lots of nailing   there was lots of nailing  
there was lots of nailing   holding walls in place while being secured   Lifting of the walls  
Throughout the day, there was lots of nailing, lifting and carrying and then holding walls in place while being secured.

holding walls in place while being secured

 

holding walls in place while being secured

  holding walls in place while being secured  

By end of day, most outer walls were in place as were some inner walls.

Tuesday, April 29, 2008

completing the exterior walls

 

completing the exterior walls

  completing the exterior walls  
Tuesday was a beautiful day with clear blue skies and hot Louisiana sun. A great day for building.

working on interior walls

 

adding insulation and working on interior walls

  adding insulation and working on interior walls  

adding insulation and working on interior walls

 

adding insulation and working on interior walls

  adding insulation and working on interior walls  
Most of the day was spent completing the exterior walls, adding insulation and working on interior walls.

add blessings and prayers to the many of the walls

 

add blessings and prayers to the many of the walls

  add blessings and prayers to the many of the walls  

taking pictures with homeowners

 

taking pictures with homeowners

   
We made time to add blessings and prayers to many of the walls as well as taking pictures with homeowners and of course, taking brief time-outs throughout the day.

Two volunteers from the Costa Rica Baptist Federation

 

four of the five homes are ready for roof trusses

  four of the five homes are ready for roof trusses  
Two volunteers from the Costa Rica Baptist Federation share a moment with homeowner Carlas. By days end, four of the five homes are ready for roof trusses and the remaining insulations
Wednesday, April 30, 2008

Wednesday was another beautiful day with clear blue skies and hot Louisiana sun.  A great day for building…

Third Baptist Team from Saint Louis, MO.

 

Task List

  Preparing for Roof trusses  

Third Baptist Team from Saint Louis, MO. Just a few of the volunteers from the Great Rivers region.

 

The task list is back!

  Preparing for roof trusses  

preparing for and raising roof trusses

 

preparing for and raising roof trusses

  preparing for and raising roof trusses  

Most of the day was spent preparing for and raising roof trusses. First one roof, then another, and another and yet still one more.

preparing for windows and then installing windows.

 

preparing for windows and then installing windows.

   

Those volunteers not working with the roof trusses were busy preparing to install the windows.

installing roof trusses.

 

installing roof trusses.

  installing roof trusses.  

By days end, roof trusses have been installed on four of the five houses.

Thursday, May 1, 2008
Staying on task with our popular task lists   something to drink but what color would you like, red, blue or clear   Volunteers from the Great Rivers region.  

Staying on task with our popular task lists.

 

The question of the day was not if you wanted something to drink but what color would you like, red, blue or clear?

 

Volunteers from the Great Rivers region.

 
Volunteers from Bethlehem Baptist Church   Volunteers from First Baptist Church, Paris, IL   popular task lists  

Volunteers from Bethlehem Baptist Church

 

Volunteers from First Baptist Church, Paris, IL

  Our popular task lists  

a day dedicated to the roof

 

a day dedicated to the roof.

  a day dedicated to the roof  

a day dedicated to the roof

 

a day dedicated to the roof

  a day dedicated to the roof  

a day dedicated to the roof

 

a day dedicated to the roof

  a day dedicated to the roof  

Thursday was a day dedicated to the roof.

Friday, May 2, 2008
Volunteers working on the Red House   Volunteers working on Bridget's home   installing windows  

Volunteers working on the Red House

 

Volunteers working on Bridget’s home

 

Installing the windows

 
Working on the roof   Working on the roof   working pn the roof  
working on the roof   working on the roof   working on the roof  

Friday was another day dedicated to working on the roof…

bathtubs, hot water heaters and some copper piping   bathtubs, hot water heaters and some copper piping   bathtubs, hot water heaters and some copper piping  

Two homes had bathtubs, hot water heaters and some copper piping installed by the end of the day. This is the first of the contractor work.

Hot water heater   Dr. Wright-Riggins shares a moment with Homeowner Madeline   This binder contains it all  
Hot water heater   Dr. Wright-Riggins shares a moment with Homeowner Madeline   This binder contains it all, house plans, safety measures and all how to dos. It is PRICELESS!  
Saturday, May 3, 2008

Because of thunderstorms late Friday night and early Saturday morning, much work wasn’t done on the five homes, but dedicated volunteers were able to lay the sod on several new homes.

dedicated volunteers were able to lay the sod   much work wasn't done on the five homes   dedicated volunteers were able to lay the sod  
much work wasn't done on the five homes   dedicated volunteers were able to lay the sod   Volunteers from New Jersey join us for another year  
        Volunteers from New Jersey join us for another year.  
Contact Us | Home | Privacy Policy | Get Involved!
© 2007 National Ministries
American Baptist Churches USA